Projects

Lincoln B2 West Fueling Facility

Click to view larger version.

Owner    Burlington Northern Railroad Company
Architect/Engineer    APA, Inc.
Value    $6,050,000

Lincoln B2 West Fueling Facility involved construction of a new fueling facility on the south side of Hobson Yard, near its western end. Work included a diesel fuel oil loading/unloading facility, fueling platform, underground utilities and structures. We also constructed a new diesel fuel oil tank at the Cushman site west of 40th Street.

Minuteman II Dismantlement, Whiteman Air Force Base, Missouri

Click to view larger version.

Owner     Department of the Army, Omaha District, Corps of Engineers
Architect/Engineer    U.S. Army Engineer District, Corps of Engineers, Omaha, Nebraska
Value    $6,500,000

As a sub-contractor to M.A. Mortenson Company, Judds Bros. Construction Co. completed all appurtenant work to dismantle150 Minuteman Intercontential Ballistic Missile (ICBM) Launch Facilities using mechanical demolition methods to remove and dispose of the topside appurtenances and all below grade construction to the required elevations.

Lincoln Water System, Modifications to Water Pumping Stations

Click to view larger version.

Owner    City of Lincoln, Nebraska
Architect/Engineer    Olsson Associates & Black & Veatch
Value    $3,995,000

Judds Bros. Construction Co. is furnishing and installing piping, pumps, pump motors, flow tubes, butterfly valves, electrical transformers, switchgear, instrumentation and control equipment, and all other appurtenant work to "A" Street, Belmont, Merrill, Southeast and 51st Street Pumping Stations.

48" Water Main in McKinley WC7746

Owner    Metropolitan Utilities District
Architect/Engineer    Metropolitan Utilities District
Value    $2,055,000

We Installed approximately 9,300 LF of 48" Ductile Iron Water Main and relocated approximately 950 LF of 8" Ductile Iron Water Main from 48th and McKinley Street to 63rd and Rainwood Road

Solids Handling and Processing Improvements, Northeast Wastewater Treatment Facility

Click to view larger version.

Owner    Lincoln Wastewater System
Architect/Engineer    HDR Engineering, Inc.
Value    $4,055,000

Construction of two (2) 2,000 gpm production wells with masonry well houses and approximately 1,100 LF of 16-inch diameter transmission main.

Kerford Crushing Mill

Click to view larger version.

Owner    Kerford Limestone Company
Architect/Engineer    Butler Manufacturing and STS Companies, P.C. Engineers/Consultants

Construction of a 110 LF x180 LF pre-engineered building.



 

Kerford Limestone - New Mine Entrance

Click to view larger version.

Owner    Kerford Limestone Company
Architect/Engineer    Chuck Soukup
Value    $750,000.00

Install foundations, conveyors, transfer points, crushing equipment and associated equipment in the construction of a new underground limestone mine.

Millwright Customers

Judds Bros. Construction Co. has also established themselves doing time and material work for local Companies in and around the Lincoln, Nebraska area. We have cultivated relationships with the following customers:

Kerford Limestone: Frank Cranston
Purina Mills: Kent Zimmerman
Crete Mills (Lauhoff Grain): Steve Slaven
Deeter Foundry: Jeff Tomhave
Nebraska Ash Company: Tex Leber

Sanitary Sewer - Phase 2, Collection and Treatment System, (Betty, Chris & Hanson Lakes)

Click to view larger version.

Owner    Sanitary and Improvement District No. 101 of Sarpy County, Nebraska
Architect/Engineer    Olmsted & Perry Consulting Engineer, Inc.
Value    $4,200,000.00

Treatment System - Judds Bros. Construction Co. built an on-site constructed wetlands wastewater treatment system, consisting of site grading, splitter structure, pretreatment tanks, filter tanks, subsurface constructed wetlands system, dosing tank, pumps, piping, flow meter, UV disinfection system, control building and related appurtenances.

Railroad Transportation Safety District, Railroad Track Consolidation Project

Click to view larger version.

Owner    City of Lincoln, Nebraska
Value    $3,950,000.00

The work of this project consisted of the construction of railroad trackbed and tracks, including bridge structures and miscellaneous related work for the consolidation of railroad services in Lincoln, Nebraska. The rail work of this project included the following activities:
 
The complete construction of new tracks, including subgrade for new tracks for the Omaha, Lincoln & Beatrice Railway.
The reconstruction of roadway approaches to the BNSF railroad grade crossings on 14th and 17th Streets, the construction of new subgrade for new railroad crossings of those roads and the placement of temporary pavement in the future track area.
The removal of abandoned Union Pacific Railroad tracks and other facilities in the "X" Street corridor between the BNSF, in the vicinity of 10th Street and approximately 19th Street, including the reconstruction and restoration of intersecting streets and sidewalks, the clearing and seeding and mulching of the railroad right-of-way and miscellaneous work.

Lancaster Event Center

Click to view larger version.

Owner    Lancaster County Agricultural Society, Inc.
Architect/Engineer    Design Associates
Value    $6,550,000.00

Judds Bros. Construction Co. coordinated and performed work to complete the construction of a public, multipurpose year round facility designed to host a variety of local, regional and national events and activities. The center features three interconnected structures that include the multi-purpose arena, and two multi-purpose pavilion adjacent to an outdoor arena. The multi-purpose arena is a rectangular 65,500 SF area. Pavilion I and Pavilion II are 80,000 SF each.

Lincoln Water System, Expansion of Water Supply, Treatment and Transmission Facilities, Northeast Pumping Station and Reservoir Modifications

Click to view larger version.

Owner    City of Lincoln, Nebraska
Architect/Engineer    Lincoln Water Consortium: Black & Veatch, HWS Consulting Group, Inc., Olsson Associates, Sinclair Hille & Associates
Value    $5,675,000.00

The contract included construction of a 5.1 million gallon below-grade ground storage treated water reservoir of cast-in-place concrete construction and associated 48-inch and 54-inch yard piping adjacent to the existing Northeast Pumping Station and Reservoir. A single 20.2 mgd low head pumping unit was installed and wetwell modifications provided in the existing Northeast Pumping Station, along with modifications of the facilities electrical and heating, ventilation, and air conditioning systems.

Lincoln Water System, Expansion of Water Supply, Treatment and Transmission Facilities, Vine Street Pumping Station and Reservoir

Click to view larger version.

Owner    City of Lincoln, Nebraska
Architect/Engineer    Lincoln Water Consortium: Black & Veatch, HWS Consulting Group, Inc., Olsson Associates, Sinclair Hille & Associates
Value    $7,800,000.00

The contract included construction of a 10 million gallon below-ground storage treated water reservoir of cast-in-place concrete construction with a High Service Pumping Station integrally constructed within the new reservoir. The reservoir and pumping station were constructed adjacent to the existing 10 million gallon Vine Street Reservoir. Two 10 mgd vertical diffusion vane pumping units were furnished and installed in the pumping station. The contract also included construction of a reservoir overflow structure, flow control vault, meter manhole, retaining walls, major yard piping ranging from 54-inch to 20-inch diameter, piping and electrical modifications at the existing Vine Street Pumping Station and associated electrical work, control and instrumentation work, mechanical work, site work, and all other appurtenant work.

Carlos Street Water Improvement

Click to view larger version.

Owner    City of Lincoln Water System
Architect/Engineer  Kirkham, Michael, Schemmer and Associates
Value   $ 3,500,000.00

The project included the furnish and install of 5,600 LF of 54 inch steel water main.  Also relocation of 8 inch sanitary sewer on Carlos Drive and various storm sewer extensions.  The below ground improvements also includes the removal and repaving of Carlos Drive from East Avon Lane to Holdredge Street.

ADM Dry Mill Underground

Click to view larger version.

Owner  Archer Daniels  Midlands
Architect/Engineer    N/A
Value    $672,280.00

The project included installation of 10,000 LF of 16-inch ductile iron fire main and all appurtenant work.  Also installed 3,300 LF of carbon steel chilled water supply and return line ranging in size from 30-inch thru 78 inch.  There is also installation of 5,280 LF of 8 inch sanitary sewer and associated manholes.  All piping was below ground.  Owner furnished all pipe and appurtances.

City Mission Addition, Lincoln, NE

Click to view larger version.

Owner:  Curtis Center Housing,  L.P.
Architect/Engineer     Design Associates of Lincoln, Inc
Value     $ 2,500,000.00

Judds Brothers Construction Co.  coordinated and performed work to complete the construction of a single level, multi-purpose facility designed as a male housing unit.  There is 18,000 SF of space including two interior court yards and a new dining room incorporated into this project. The wood framed addition has a masonry exterior and is complete with mechanical and electrical work.  This is a year around addition with a sprinkler system.

Council Bluffs Energy Center Rail Expansion

Click to view larger version.

Architect/Engineer:  Burns & McDonnell
Value of Project:  $1.48 million

The construction for this project included a new rail overpass consisting of installing a 31 ft. diameter culver to allow for train traffic to go under the new access road over the track.  The project included the grading for the overpass, relocation of existing waterlines, the laying of the culvert pipe allowing the track to go underneath the new overpass, laying of new track going through the culvert, storm drainage, paving of the new road on the overpass, signage and street lighting.

Northeast Community Recreational and Sports Complex

Click to view larger version.

Owner    Joint Antelope Valley Authority (JAVA)
Architect/Engineer    Parsons Brinckerhoff, Olsson Associates, Sinclair Hille Associates
Value    $3,279,000

The project includes construction of four (4) ball fields, multi-purpose field, multi-purpose courts, concession building, picnic shelter, parking lot, removal and installation of railroad track, loadout building and associated work for completion of the project.

Brownell Elementary School and Multi-purpose Room and Indoor Air Quality Project

Click to view larger version.

Owner    Lincoln Public Schools
Architect/Engineer    Architectural Design Associates, P.C.
Value    $3,517,000

Addition of a Multi-purpose Room and renovations associated with a new heat pump system. 

Lincoln East High School Classroom Addition

Click to view larger version.

Owner    Lincoln Public Schools
Architect/Engineer    Sinclair Hille and Associates, Inc.
Value    $4,000,000

Judds Bros. Construction Co. performed the work to complete this project, which involved the new construction of general-purpose classrooms, science classrooms/labs, ancillary science rooms, teacher work areas and the enclosing of an existing exterior courtyard for use as a multi-purpose room. The remodeling portion of the contract included remodeling the existing science classroom/labs, teacher work areas and sprinkler system. There was approximately 36,000 SF of new construction and 14,000 SF of remodeled space incorporated into this project. Judds Bros. Construction Co. completed the steel erection with our own forces and also various miscellaneous appurtenant tasks.

I-80 Scales and Scale Buildings

Click to view larger version.

Owner    The Nebraska Department of Road s
Architect/Engineer    Davis Design
Value    $2,800,000

Largest scale site in the State of Nebraska, consisting of four buildings, two operation stations and two truck inspection facilities. The Nebraska State Patrol Carrier Enforcement Division for certifying legal weight limits of commercial vehicles and inspection of the same operates this facility. This was a highly technical project featuring Nebraska's only weigh station to have both directions of traffic equipped with a Weight In Motion (WIM) scale system. This project involved a short time frame with coordination between Judds Bros. Construction Co., the paving contractor and the owner, which made this a truly unique project.

Judds Bros. Construction Co. completed all structural work on this project including the foundations, wood framing, pre-engineered buildings, floor slabs, inspection pits, and the WIM vaults incorporated into interstate I-80.

The construction included a unique round design for high visibility of interstate traffic, and incoming and outgoing vehicles. The conical roof framing with its complex design required highly skilled carpenters. There are also truck inspection pits for easy access to the underside of vehicles. The Static Scales are designed and built for years of service at an estimated 24,000,000 trucks per year. The Weight In Motions Scales are employed as a sorting device to aid in the selection of trucks to be brought into the station for weighing.

Dawes Middle School Indoor Air Quality Improvements

Owner    Lincoln Public Schools
Architect/Engineer    Architectural Design Associates, P.C.
Value    $4,424,000

Renovation of existing facility which included new heating, cooling, and electrical systems, a geothermal well field, and penthouses.  Construction of new roofing system and fire protection system for existing structure.

Faith Lutheran Church, Phase I & II

Click to view larger version.

Owner    Faith Lutheran Church
Architect/Engineer    JEO Consulting Group, Inc.
Value    Phase I - $2,800,000, Phase II - $2,400,000 

The project consists of the construction of an approximate 30,000 square foot, two story, steel framed, composite slab, steel stud/masonry/EFIS exterior, steel stud interior partitions, complete with all mechanical and electrical work.

Platte West

Click to view larger version.

Owner:  Metropolitan Utilities District
General Contractor:  Alberici Constructors, Inc
Architect/engineer:  HDR
Value: $7,794,116.00

Judds Bros Construction Co provided all supervision, labor, material, tools, and equipment to complete all yard piping from 1 inch through 72 inches including civil site, drainage, chemical injection vault and appurtenances.  The project also included manholes, inlets, junction boxes, drain boxes, flared inlet sections, pond inlets, and outlets and chemical duct banks.  There are 92,000 LF of pipe involved.